Most gas-insulated switchgear failures in the first two years are not design failures. They are installation failures: a room that cannot relieve pressure, a busbar joint torqued to feel rather than to a number, a gas compartment filled with humid air, a cable screen left floating. None of these show up on the delivery paperwork. All of them show up later as partial discharge, gas top-ups or a protection trip that will not reset.
This checklist is the twelve points we verify before energising a GIS installation, written in the order they occur on site. Each point carries the acceptance number we use, so it can be dropped into a method statement or a commissioning protocol without rewriting.

The Twelve Checks at a Glance
| Stage | Check | Acceptance |
|---|---|---|
| Before | Room, floor, trench, cleanliness | Flatness ≤ 2 mm/m, earthing ≤ 0.1 Ω |
| Assembly | Transport, torque, gas filling, leak test | Dew point ≤ −36 °C, leak ≤ 0.1 %/year |
| Commissioning | PD, interlocks, withstand, protection | PD ≤ 10 pC, 80 % withstand, timing verified |
Stage 1 — Before the Room Is Ready
1. Room dimensions and pressure relief
A GIS room is not storage. It needs clear height of equipment height plus at least 500 mm for lifting and gas handling, front access for the operating mechanism, and a pressure relief path sized by the manufacturer. In an indoor installation the relief duct must vent outside, not into the cable basement. If a compartment ruptures during an internal arc, that duct is the only thing keeping the arc products away from the operator.
2. Floor flatness and anchor points
Check flatness with a 2 m straight edge: the allowed deviation is 2 mm per metre, and no step at a joint. Anchor positions must sit within ±5 mm of the drawing. A 3 mm shim under one corner of a 4-panel lineup transfers to the busbar joint, and a tilted busbar is a partial discharge site for the next twenty years.
3. Cable trench, earthing grid and fire barrier
Measure earth continuity from the switchgear frame to the main earth terminal: 0.1 Ω or less, measured with a four-wire instrument, not a multimeter. Confirm the cable trench drains and that the fire barrier between the trench and the room is complete before any panel is set in place. Retrofitting a barrier under an installed lineup is the most expensive hour on the project.
4. Cleanliness, humidity and dust
Indoor GIS is assembled in air it will never see again. Keep relative humidity under 70 % during assembly, keep the room free of grinding dust from civil works, and cover open gas compartments the moment a flange is removed. A single bag of cement dust in an open busbar chamber is enough to fail the partial discharge test two weeks later.
Stage 2 — During Assembly
5. Transport damage and gas pre-charge
Before unpacking, read the shock and tilt indicators, photograph them, and record the transport gas pressure. Factory-sealed compartments normally ship at a slight positive pressure of 0.02–0.05 MPa; a reading near zero means a seal has opened in transit. Never accept a panel with a lost pre-charge without a leak test on site.
6. Busbar and cable termination torque
Torque every connection with a calibrated wrench and mark it. Typical values are 45–50 N·m for M12 and 80–90 N·m for M16, applied to clean, greased contact surfaces. After torquing, measure contact resistance and compare with the factory sheet: a joint reading more than 20 % above the reference is a re-work, not a pass.
7. Gas filling, purity and dew point
Fill through a service cart with a filter-drier, never from a bottle straight into the compartment. Accept SF6 at 97 % purity or better by volume, and hold the dew point at −36 °C or lower, which corresponds to roughly 250 ppmv moisture. Record the ambient temperature and the filling pressure at the time of filling: the same compartment reads differently on a cold morning.
8. Leak test per compartment
Test each gas zone separately, at the declared pressure, with a calibrated sniffer or the accumulation method. The acceptance is 0.1 % of the compartment gas mass per year. A leak inside the limit still needs a note in the handover file, because the top-up interval over a 30-year life is calculated from that number.

Stage 3 — Commissioning
9. Partial discharge after assembly
Run the PD measurement with the couplers in the same positions used at the factory, and with the background noise recorded first. On site we accept 10 pC; anything above is located with an acoustic or UHF probe before energisation, not after. This is the check that catches a busbar that was clean in the workshop and contaminated on site.
10. Interlocks and earthing continuity
Operate every interlock by hand: the earthing switch cannot close with the breaker closed, the compartment cannot be accessed with the switch closed, the breaker cannot be racked in with the earth switch closed. Then re-measure earth continuity at each panel, not only at the lineup end.
11. Site power-frequency withstand
Where the specification requires it, apply 80 % of the factory test voltage for one minute, phase to earth and across the open gap, as allowed for site testing. Hold the record with the ambient conditions. If the site test is waived, say so in the handover file rather than leaving the column blank — an empty line reads as a missed test, not as a waiver.
12. Protection settings, breaker timing and SCADA
Inject current into every protection relay, verify the trip and alarm contacts, and measure breaker opening time against the type-test value (typically 60 ms or less for a medium-voltage vacuum interrupter). Then check the point list against the SCADA display one signal at a time. The most common commissioning delay is not a failed test; it is a signal mapped to the wrong panel number.
The Numbers That Decide Acceptance
| Parameter | Limit we apply | Instrument |
|---|---|---|
| Floor flatness | ≤ 2 mm/m, no step | 2 m straight edge, feeler gauge |
| Earth continuity | ≤ 0.1 Ω | Four-wire earth tester |
| Gas moisture | ≤ 250 ppmv (−36 °C dew point) | Dew-point meter at the valve |
| Leak rate | ≤ 0.1 %/year per zone | Calibrated sniffer / accumulation |
| Partial discharge | ≤ 10 pC on site | UHF / acoustic with noise baseline |
| Breaker opening time | ≤ type-test value, typically 60 ms | CB timing analyser |
The limits follow IEC 62271-200 for the assembly, IEC 62271-1 for general requirements and IEC 62271-203 above 52 kV. Where a project specification is stricter, the project number governs and the factory sheet is re-checked against it before the panel leaves the workshop.

Mistakes That Cost a Year of Delay
Four failures account for most of the site delays we see. Filling gas before the compartment has been evacuated, which traps moisture behind the seal. Torquing aluminium busbars with the values written for copper. Testing leak rate on a lineup instead of per zone, so the good compartments hide the one that leaks. And commissioning protection relays from a template instead of the approved setting sheet, which passes the test and fails the audit.
None of the twelve checks needs special equipment beyond a dew-point meter, a four-wire earth tester, a calibrated torque wrench and a PD set. What they need is the discipline to record each number on the day it was measured. If you are still at the specification stage, the choice of SF6 versus solid insulation and the sizing of the ring main unit decide how much of this checklist you will be running at all.
FAQ
Does a site power-frequency test replace the factory type test?
No. The type test qualifies the design once; the site test only proves the assembled insulation survived transport and assembly, which is why it is run at 80 % of the factory value for one minute.
What dew point is acceptable at handover?
−36 °C or lower, which is about 250 ppmv. Above that, the compartment is topped up and re-measured after 24 hours, because moisture migrates through the gas before it settles.
How long after installation can the switchgear be energised?
When the twelve records are complete, typically within one working day of the last test. If the PD or leak test is outstanding, energisation waits — those two cannot be repeated safely once the lineup is live.
Is a 0.1 %/year leak rate realistic in a hot climate?
Yes, if the seals are correct and the compartment pressure was set at the filling temperature. Pressure rises with temperature, so a compartment filled cold and checked hot will look like a leak when it is only expansion.
What documents should the handover file contain?
The twelve test records with instrument serial numbers, the gas filling sheet with purity and dew point, the torque marking sheet, the relay setting sheet as approved, and the PD and withstand reports. Buyers who ask for this file at tender stage usually get a better installation.
Send us your single-line diagram and room layout and we will return a marked-up installation checklist for your voltage class, with the acceptance numbers filled in. Write to info@chngs-electric.com or message us on WhatsApp at +86 135 8897 8050. Related reading: what a ring main unit is, SF6 versus solid insulation, RMU versus VCB and how to size an RMU.