Tested to the clause, not to the brochure
Metal-enclosed switchgear
Ratings, interlocks, IP classification, internal arc and loss-of-service-continuity category.
Load-break switches
Closed-loop and cable-charging breaking currents — the two values buyers should always ask for.
Circuit breakers
Breaking and making capacity, operating sequence, mechanical endurance.
Process records
Material, welding, gas-filling and test records archived per serial number.
The four tests every unit passes before it ships
A routine test is not a formality. Every unit that leaves the factory goes through power-frequency withstand, partial discharge measurement, a gas leak check and a mechanical operation sequence — and the numbers go on a record tied to the serial number, not on a generic certificate.
Type tests are a different matter. Type tests qualify a design: they are done once, on a representative arrangement, at an independent laboratory, and they define what the factory is allowed to build. That is why at 33 kV we ask for the type-test requirement before quoting — the arrangement has to match the report, or the report does not cover it.
What this means for your project
- Power-frequency withstand — phase–earth and across the open gap at the declared level for the class.
- Partial discharge — measured at 1.1 × Um / √3; the limit is what separates a good casting from a marginal one.
- Gas leak — helium or pressure-decay check on the sealed tank; declared loss is ≤ 0.1 % per year.
- Mechanical operation — close/open cycles on the breaker and the earthing switch, with the mechanism checked for the declared endurance (5,000 operations on GSRM6).