RMU Earthing Switch: Interlock Sequence and 6 Commissioning Checks

CHNGS GSRM6 gas-insulated ring main unit, three-way configuration

The earthing switch inside a ring main unit is the only device standing between a technician and a live cable. It is mechanically simple — a set of contacts that shorts the conductor to the earthed tank — but the logic around it, the interlock chain and the operating order, is where most mistakes happen in the field.

This guide walks through how the interlock chain actually works on a gas-insulated RMU, the exact operating sequence for cable earthing, and six checks to run before you energize a new unit.

Why the Earthing Switch Is the Last Line of Defence

An RMU feeder has three states: closed (carrying load), open (isolated but the cable may still be charged or back-fed), and earthed. The earthing switch is not a load-break device and it is not meant to interrupt current. It is a maintenance device that makes the cable safe to touch.

Three conditions make that distinction important:

Back-feed. A ring feeder can be energized from the far end by another substation or by a generator. Opening the local switch does not de-energize the cable.

Capacitive charge. An open cable retains charge. Without earthing it can deliver a shock even when every switch on the panel reads open.

Faulted cable. If the cable has failed, closing the earthing switch onto a live fault creates an arc. This is why the interlock must prevent closing the earthing switch while the load-break switch is closed.

Two ratings matter on the nameplate and both are often misread: the short-time withstand current, usually 20 kA for 1 s or 3 s, and the making capacity of the earthing switch itself. The second number decides whether the switch can safely be closed onto a cable that turns out to be faulted — the case where a mistake becomes an arc. Confirm both against the system fault level before installation, not after.

The earthing switch is sized to carry the short-circuit current for the short time needed to trip upstream protection, typically 1 s or 3 s at 20 kA. It is not a continuous-current device.

How the Interlock Chain Works

On a typical SF6 RMU the three positions are linked mechanically, not electrically. The interlock is a set of cams, levers and a key or padlock point that enforce one sequence only:

1. The load-break switch must be open before the earthing switch can be closed.
2. The earthing switch must be open before the load-break switch can be closed.
3. The cable compartment access panel cannot be opened unless the earthing switch is closed.
4. The earthing switch cannot be opened while the access panel is open (on the better designs, a key trapped in the panel).

Some panels add a second interlock to the fuse or the CT compartment. On units with a motor-operated mechanism, the same logic is implemented in the control circuit as well, but the mechanical interlock must remain the primary protection — see our notes on RMU protection choices for how this differs between switch-fuse and circuit-breaker designs.

Interlock Condition Mechanical Means Typical Failure Mode
Load-break closed → earthing blocked Cam on operating shaft Bent cam after forced operation
Earthing open → cable panel locked Trapped key or bolt Panel forced open with a bar
Panel open → earthing cannot open Key trapped in panel Key duplicated or bypassed
Earthing closed → load-break blocked Linkage to switch shaft Linkage removed during service
Motor operation only when earthed state allows Limit switch in control circuit Limit switch bypassed in a hurry

Operating Sequence for Cable Earthing

Follow this order every time, and never assume the previous shift left the panel in a safe state.

1. Confirm identity. Read the panel label and the single line diagram, not the cable number painted on the floor. Cross-check with the RMU symbols on the drawing.

2. Open the load-break switch. Confirm the mechanical indicator reads OPEN and, on motorized units, that the auxiliary contact confirms it.

3. Prove dead. Test the cable side with a voltage detector rated for the system voltage. Do this before touching the earthing switch handle.

4. Close the earthing switch. Use the operating handle; listen for the contact closing and confirm the position indicator. This is a no-load operation.

5. Open the access panel. Only now is the panel interlock released. Apply the personal lock and tag.

6. Re-test at the conductor. On the exposed conductor, confirm no voltage again. Earthing protects against re-energization, not against an existing fault.

rmu earthing switch and interlock on a GSRM6 ring main unit panel

A three-way RMU panel with the earthing switch handle and position indicator at the front. The interlock cam sits directly behind the operating shaft.

Six Checks Before You Commission

On a new unit, the interlock is the first thing to verify on site, before any cable is terminated.

Check 1 — Try to defeat it. With the load-break switch closed, attempt to close the earthing switch. It must not move. Repeat with the panel open: the earthing switch must not open. If either moves, stop.

Check 2 — Confirm the indicator, not the handle. The handle position and the mechanical indicator should agree at every step. A mismatched indicator means a broken linkage.

Check 3 — Test the auxiliary contacts. On motorized panels, verify the limit switch prevents motor closing while earthed and prevents earthing while closed.

Check 4 — Verify the earthing path. Measure the resistance from the earthing switch contact to the tank earth point. It should be a fraction of an ohm, not tens of ohms.

Check 5 — Confirm the panel lock. The trapped key or bolt must be present and functional; a missing key is the most common reason a panel gets forced open.

Check 6 — Record the routine test data. The factory test report should show the earthing switch short-time current and the interlock functional test, as described in our RMU routine test guide.

rmu tank cutaway showing earthing switch contacts inside the gas tank

A tank cutaway: the earthing contacts sit inside the gas enclosure, connected to the tank body. There is no way to inspect them without opening the tank, which is why the interlock verification is done mechanically.

Common Field Mistakes

Earthing the wrong feeder. In a ring with two incoming ways, the label on the panel and the cable schedule can disagree after a modification. Always identify by test, not by label.

Closing the earthing switch on a charged cable. This produces an arc and can rupture the panel. The voltage check in step 3 is not optional.

Bypassing the key interlock. Duplicated keys, removed linkages and “temporary” bypasses are how panels get opened while live. Any bypass must be recorded and removed the same shift.

Not testing the interlock after every service visit. A linkage that was removed for adjustment and refitted loosely will pass a visual check and fail under load. Add the interlock sequence to the switching schedule, not just to the commissioning form.

Treating the earthing switch as a load-break device. It has no arc-quenching capability. Opening it under load damages the contacts and may not clear the arc at all.

Ignoring the second feeder. After maintenance, both ways must be restored in the correct order — our fault location guide covers what to check when the ring is restored.

interlock functional test during rmu routine testing at the factory

Interlock functional testing in our test bay: every panel is operated through the full sequence before dispatch.

FAQ

Can the earthing switch be closed with the load-break switch closed?

No. The mechanical interlock blocks it, and it must never be forced. If it moves, the interlock is damaged and the unit must not be energized.

How long can the earthing switch carry fault current?

Typically 1 s or 3 s at the rated short-time current, for example 20 kA. It is not designed for continuous current or repeated operations under fault.

Is the interlock mechanical or electrical?

On SF6 RMUs the primary interlock is mechanical — cams, links and trapped keys. Electrical limit switches on motorized units are a secondary layer, not a replacement.

What if the position indicator disagrees with the handle?

Stop and investigate the linkage before operating. A disagreement means the internal state is unknown, which is the most dangerous condition on any switchgear.

Does the cable need to be discharged before earthing?
Closing the earthing switch discharges the cable capacitance through the earthing contacts, which is exactly what the device is for. But confirm no live source first — discharging is not the same as proving dead.

About CHNGS Electric

CHNGS Electric builds SF6 and solid-insulation ring main units, GIS and RMU panels in Yueqing, China, with mechanical interlock verification on every unit before dispatch. We can supply the interlock logic drawing and routine test data with each panel. Contact info@chngs-electric.com or WhatsApp +86 135 8897 8050. Related reading on our sister sites: transformer winding resistance checks for MV substations, and LV switchgear forms of separation.